The new road has not been finished and the contractors have now left the site
Reported via desktop in the Current Roadworks - live information category anonymously at 13:53, Mon 27 December 2021
Sent to Oxfordshire County Council less than a minute later
After 2 years of work the road between Grove and Wantage is still not finished properly and there doesn't appear to be any contractors on site. The junction point between the new road and the original road is already starting to break up.
Council ref: ENQ21912596
Updates
-
State changed to: Investigating
Updated by Oxfordshire County Council at 13:53, Mon 27 December 2021
-
Its outside my drive at 1 Albermarle Drive,Grove. Just outside the kerb on the road. BT contractors were working yesterday snd today right beside it and when I why they didnt fill the poor road right beside where they were filling with tar they said that is the council. I am, therefore, writing to you about it. They said they took photos snd would be reporting it.
Posted anonymously at 20:19, Tue 7 June 2022
-
Apologies for the delay in response. Due to the length of time since it was reported please can you confirm if it is still an issue by creating another report on Fix My Street.
State changed to: Investigation complete
Posted by Oxfordshire County Council at 17:49, Tue 31 October 2023
This report is now closed to updates from the public. You can make a new report in the same location.