Back to all reports

Abandoned roadworks left in an unsafe state by Crest Nicholson

Reported via desktop in the Roads/highways category anonymously at 17:39, Thu 18 November 2021

Sent to Oxfordshire County Council less than a minute later

No progress has been made on these roadworks in the past four months, and have been abandoned by the developer, Crest Nicholson. The red and white barriers which are on the road are next to an excavation for the supposed pathway which has not been completed. The road surface around the traffic islands which were hastily added to attempt to address the issue of speeding and safety is also unfinished.

Council ref: ENQ21910451

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your enquiry. This issue has been passed onto the relevant team for investigation.

    State changed to: Investigating

    Posted by Oxfordshire County Council at 17:40, Thu 18 November 2021

  • Dear Mr Gillott,

    Oxfordshire County Council are working with Crest Nicholson to have the highway works completed as soon as possible.

    Kind regards
    Road Agreements Team

    Posted by Oxfordshire County Council at 12:46, Tue 30 November 2021

  • Developer will be completing these works.

    State changed to: Investigation complete

    Posted by Oxfordshire County Council at 12:50, Tue 30 November 2021

This report is now closed to updates. You can make a new report in the same location.