Back to all reports

Rutting not completed

Reported via desktop in the Roads/highways category anonymously at 12:20, Friday 17 September 2021

Sent to Oxfordshire County Council 5 minutes later

Thank you for filling in the rutting so far - but it looks as if you ran out of material and only about 25% of the rutting has been filled. It is still dangerous - see photos.

Council ref: ENQ21905683

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your enquiry. This issue has been passed onto the relevant team for investigation.

    State changed to: Investigating

    Posted by Oxfordshire County Council at 12:21, Friday 17 September 2021

  • We have investigated your report and this issue has been added to a programme of work.

    State changed to: Investigation complete

    Posted by Oxfordshire County Council at 12:41, Thursday 23 September 2021

This report is now closed to updates. You can make a new report in the same location.