Pothole due to new drainage
Reported in the Pothole category anonymously at 09:00, Tue 18 August 2020
Sent to Oxfordshire County Council less than a minute later
Workman having done work but have left tarmac uneven and very low.
Council ref: ENQ20873859
Updates
-
Thank you for your enquiry. This issue has been passed onto the relevant team for investigation.
State changed to: Investigating
Posted by Oxfordshire County Council at 09:01, Tue 18 August 2020
-
This is not drainage, it is a stop cock for the supply of fresh water to the new build in Boscher’s yard. Th cause is incorrect back-fill material, (viz ballast instead of MOT type 1)
Posted anonymously at 04:31, Wed 19 August 2020
-
This is getting significantly worse and will, if not already has done, cause a lot of damage to a vehicle or cyclist. It really needs to be fixed within the next day.
Posted anonymously at 23:24, Mon 24 August 2020