Back to all reports

4 street lights not working

Reported in the Street lighting category anonymously at 21:35, Thu 4 January 2018

Sent to Oxfordshire County Council 4 minutes later

Along the footpath between Radley Green and Peachcroft, streetlight nos. 27 and 28 are not working and along the footpath running parallel to the stream numbers 17 and 18. I think there might be a few more. It's very dark in these areas at night now.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report; we have logged this as a fault on our management system. Our current policy is for our contractor to attend electrical & structural emergencies as a priority; these will be attended within a 24hr period. All other faults are logged on our management system, for efficiency, these are grouped by area and the date they were reported, and the contractor attends against a programmed of works based on this approach.

    State changed to: Action scheduled

    Posted by Oxfordshire County Council at 09:26, Fri 5 January 2018

  • All these lights are still not working as previously reported. Need to be fixed ASAP

    Posted anonymously at 19:38, Mon 15 January 2018

  • Thank you for your report, we have attended site and found that specialist equipment is required to fix the issue due to the units location, we will attend to this as soon as resources allow.

    Posted anonymously at 12:22, Tue 16 January 2018

  • These lights are still not working today - this is now over 3 weeks that the path has been dark & dangerous. surely it can't take this long to fix. perhaps a word to our MP might help!!!

    Posted anonymously at 16:14, Mon 29 January 2018

  • Unfortunately it requires specialist equipment to access and the unit is currently working within another area of the county, I apologise this is taking some time to resolve but our current policy is our contractor to attend electrical & structural emergencies as a priority; these will be attended within a 24hr period (unfortunately these units do not fall into this category. All other faults are logged on our management system, for efficiency, these are grouped by area and the date they were reported, and the contractor attends against a programmed of works based on this approach.

    Posted by Oxfordshire County Council at 08:57, Tue 30 January 2018

Provide an update

Please note that updates are not sent to the council. Your information will only be used in accordance with our privacy policy

Next: Tell us about you

Your update

Tell us about you

Do you have a FixMyStreet password?